Package 1 of the RM3 billion Juru–Sungai Dua Traffic Dispersal Project was 54.61% complete as at 8 November 2026, highway concessionaire PLUS Malaysia said. The project upgrades 17.4 km of the North–South Expressway through central Seberang Perai, between the Juru and Sungai Dua toll plazas.
The key facts
| Item | Details |
|---|---|
| Project | Juru–Sungai Dua Traffic Dispersal Project (PTJSD) |
| Cost | About RM3 billion |
| Length | 17.4 km, Juru Toll Plaza to Sungai Dua Toll Plaza |
| Package 1 | 54.61% complete as at 8 November 2026 |
| Packages 2 to 5 | At the final tender stage |
| Completion | Not announced |
Read our earlier report on the project’s progress.
What it means for industrial property
- Smoother freight. Once complete, smoother traffic on this stretch helps trucks moving goods through central Seberang Perai.
- Roadworks first. With packages 2 to 5 still to start, expect diversions for some years.
- Projects along the corridor. See our picks in Juru and Bukit Mertajam below.
Factories to consider
Our picks in Juru and Bukit Mertajam.
| Project | Area | Unit type | Built-up | SPA price | Completion |
|---|---|---|---|---|---|
| Puncak City | Juru | 2-storey light industrial units | 1,625–2,099 sq ft | RM1,165,000–RM1,978,800 | Q3 2027 |
| Machang Bubuk Signatures | Bukit Mertajam | Single-storey semi-D and detached factories with 2-storey offices | 3,802–8,070 sq ft | From RM3,860,000 | Aug–Oct 2028 |
| Machang Bubuk Signatures 2 (Bukit Teh) | Bukit Mertajam | Single-storey semi-D factories with 2-storey production offices, 6 units | 11,780–17,637 sq ft | RM10,531,000–RM13,397,000 | March 2028 |
Prices are developer SPA prices and change with availability. WhatsApp us for the latest price list and units still available.
Frequently asked questions
How far along is the Juru–Sungai Dua upgrade?
Package 1 was 54.61% complete as at 8 November 2026.
How much does it cost?
About RM3 billion.
When will it be finished?
PLUS has not announced a completion date.
Looking for a factory in Penang?
WhatsApp or call +60 10-313 9113.
Sources
- The Star: First package of Juru-Sungai Dua traffic dispersal project is 54.61% complete
- Bernama: Package 1 of Juru-Sungai Dua Traffic Dispersal Project achieves 54.61 pct completion
This article is general information based on published reports as of 19 November 2026. It is not investment advice.