The 5.7 km Air Itam–Tun Dr Lim Chong Eu Expressway bypass was 93.19% complete as at 30 September 2026 and is expected to be ready in April 2027. Chief Minister Chow Kon Yeow gave the update, The Vibes reported on 24 October 2026.
The key facts
| Item | Details |
|---|---|
| Project | Air Itam–Tun Dr Lim Chong Eu Expressway bypass |
| Length | 5.7 km |
| Cost | RM851 million |
| Progress | 93.19% as at 30 September 2026 |
| Expected opening | April 2027, after technical inspection and a road safety audit |
| Connects | Air Itam and Farlim directly to the Tun Dr Lim Chong Eu Expressway |
Penang Infrastructure Corporation CEO Datuk Seri Farizan Darus said the bypass will shorten travel times and ease congestion along Green Lane, Air Itam and Jalan Masjid Negeri.
What it means for Air Itam homebuyers
- Faster trips to Bayan Lepas and the bridge. A direct link to the expressway cuts out busy town roads.
- Less traffic on Green Lane. That helps residents of Air Itam and Farlim.
- Opening is close. Buyers now can benefit within months.
Projects to consider
Completed freehold landed homes in Air Itam.
| Project | Location | Type | Price | Completion |
|---|---|---|---|---|
| UL Residence | Air Itam | Townhouse with private lift, 3,243–3,948 sq ft, freehold | RM2,050,000–RM2,580,000 | Completed |
| Air Itam 3 Storey Terrace House | Lorong Sempadan 3, Air Itam | 3-storey terrace, 2,902 sq ft, freehold | RM1,858,000 | Completed |
Prices are developer selling prices and change with availability. WhatsApp us for the latest price list and units still available.
Frequently asked questions
When will the Air Itam bypass open?
It is expected to be ready in April 2027.
How long is it?
5.7 km.
What does it connect?
Air Itam and Farlim to the Tun Dr Lim Chong Eu Expressway.
Looking at homes in Air Itam?
WhatsApp or call +60 10-313 9113.
Sources
- The Vibes: Air Itam–Tun Dr Lim Chong Eu Expressway expected to be ready by April next year
- Penang Property Talk: Air Itam–Tun Dr LCE Expressway bypass on track for April 2027 completion
This article is general information based on published reports as of 20 November 2026. It is not investment advice.